Steel had a dramatic winter. Domestic prices sank to five-year lows in November and December 2025, then rallied hard in January 2026 as mills raised flat and long product prices month after month. Behind the swing were a new trade barrier, more expensive raw materials and builders restocking.
01The safeguard duty
In April 2025 the government imposed a 12% provisional safeguard duty, for 200 days, on certain flat steel imports after a surge of cheap shipments. At the end of December 2025 it was replaced by a three-year duty starting at 12% and tapering to 11%, running to April 2028. Crisil estimates import volumes fell about 37% between April and December 2025.
The duty targets flat products like hot-rolled coil, not TMT bars. But it lifts the whole domestic price curve, because mills set prices with one eye on what imports would cost.
02What prices did
Industry sources reported hot-rolled coil jumping from about ₹49,500 to ₹57,500 a tonne within a fortnight in January 2026. Rebar followed.
03Raw materials pushed too
Coking coal, the other big input, fell to about $175 a tonne in March 2025 and climbed back to about $246 by February 2026, according to the Ministry of Steel. Domestic iron ore prices rose 10 to 13% year on year in 2025-26. By September 2026, reports said Indian steel prices were set to rise further on coking coal costs and a revival in demand.
04Budgeting for the swings
Your structural engineer's bar-bending schedule is the only real number. As a rough guide, residential RCC frames commonly use about 3.5 to 4.5 kg of steel per square foot of built-up area, depending on design, height and seismic zone.
A 50,000 sq ft building at about 4 kg per sq ft needs roughly 200 tonnes of steel. Every ₹1,000 a tonne move in price changes the bill by about ₹2 lakh. The jump from about ₹47,600 to ₹59,800 a tonne in primary rebar between late 2025 and March 2026 would have added about ₹24 lakh to that building.
- Lock a block of tonnage at today's price for the next few slab cycles rather than buying week to week.
- Order against the bar-bending schedule, in the lengths it calls for, to cut wastage and offcuts.
- Specify the grade (Fe 500D is common for residential frames) and ask for the mill test certificate with every lot, to IS 1786.
- Compare primary and secondary producers on price and paperwork; the gap widens and narrows with the cycle.
- Use couplers where lap lengths would waste steel in large-diameter bars.
- Check the GST on the invoice: steel stayed at 18% under GST 2.0.
The duty sets a floor under steel prices. Raw materials and demand decide how far above it they go.
Sources
- Monthly economic report, February 2026 · Ministry of Steel
- Monthly economic report, January 2026 · Ministry of Steel
- Indian steel market sees 18–25% price increase following extended safeguard duty · Angel One · 20 Mar 2026
- India imposes safeguard duties on steel imports · Steel Technology · 6 Jan 2026
- In fiscal 2026, safeguard duty supported domestic steel output · EPC World (Crisil)
- Duties raise the floor, demand sets the ceiling · India Sea Trade News (S&P) · 17 Sep 2026
- Indian steel prices rally in Jan 2026 · BigMint
Before you act on this
This article is general information as of 19 Nov 2026. It is not legal, tax or investment advice. Rates, rules and market numbers change; check the sources above, and speak to a chartered accountant or an advocate about your own case.