GST 2.0 took effect on 22 September 2025. It folded most goods into two main slabs, 5% and 18%, with a 40% rate for luxury and sin goods, and largely removed the 12% and 28% slabs. For construction, a few big items moved. Many did not. A year later, it is worth being precise about which is which.
01What got cheaper
- Cement: 28% to 18%. The biggest single change for any building site.
- Marble, travertine and granite blocks: 12% to 5%. This applies to blocks. Polished slabs and tiles stay at 18%.
- Sand-lime bricks and stone inlay work: 12% to 5%.
02What did not move
- Steel, including TMT bars: 18%.
- Ceramic and vitrified tiles: 18%.
- Natural and manufactured sand: 5%.
- Ready-mix concrete and ceramic sanitaryware: 18%.
- Most clay and fly-ash bricks: still under the special scheme for brick kilns, at 6% without input tax credit or 12% with it.
03One thing went up
Works contract services for government projects moved from 12% to 18%. Contractors who bid on government work before the change and invoice after it have a margin problem unless their contract has a clause for tax changes.
04Who actually saves
The answer depends on whether you can claim input tax credit.
- Residential builders on the 1% or 5% scheme cannot claim credit, so GST on materials is a cost. Every rupee of tax cut on cement goes straight into their cost, or their price.
- Businesses that can claim credit, such as many works contractors, recover the GST anyway. For them, a lower rate mostly helps cash flow.
- People building their own homes pay the full tax and claim nothing back, so they gain the most from every cut.
JLL estimates that GST 2.0 could save 2 to 5% on construction costs, partly offsetting rising labour costs. ICRA estimated the cement cut alone would lower rural housing construction costs by 0.8 to 1%.
For cement, yes, at first: the average trade price fell by about ₹23 a bag in September 2025. Since then the pre-tax price has crept up, and by August 2026 the bag cost about ₹360 again. The cut is still worth about ₹30 a bag against what the same cement would cost at 28%.
05Your checklist
- Check the HSN code and rate on every supplier invoice; mistakes are common.
- Ask for quotes before GST, so tax changes are visible and you can compare suppliers.
- Put a change-in-law clause in supply and works contracts so tax changes pass through cleanly in either direction.
- Contractors on government work: re-price for 18% where contracts allow.
- Builders: rework the cost estimate for projects in progress; cheaper cement is a direct saving on the 1% and 5% schemes.
GST 2.0 helped the heaviest material on site. Steel, tiles and labour still decide most of the bill.
Sources
- GST reforms for home construction: what every homeowner and builder should know · Taxscan
- GST rates on construction services and materials, Sept 2025 update · Construction Placements
- GST Council cuts rates on marble, granite and sand-lime bricks · HDFC Sky
- Old and new GST rates, including works contracts · TaxGuru
- Construction Cost Guide, India – 2026 · JLL
- Cement margins seen rising 12–18% in FY26 (ICRA) · Indian Cement Review
- New GST for construction materials · Busy
Before you act on this
This article is general information as of 19 Nov 2026. It is not legal, tax or investment advice. Rates, rules and market numbers change; check the sources above, and speak to a chartered accountant or an advocate about your own case.