The plan. In rupees.
Enter the agreement value. Set what falls due at each stage. See the whole schedule, stage by stage, and check it adds to 100.
How it is worked out.
Free payment plan builder: enter the agreement value and the percentage due at each stage to see a construction-linked payment schedule in rupees. Print it or use it as a starting point.
- Each stageAgreement value × the percentage for that stage.
- SlabsThe slab percentage is divided equally across the number of slabs.
- The checkAll stages must add up to 100 percent.
- Taxes and chargesNot included. GST, stamp duty and registration are added as they apply.
- The percentages are yoursThe starting figures are an example, not a recommendation. State rules can limit what may be collected before the agreement is registered.
Quick answers
What is a construction-linked payment plan?
A construction-linked plan, or CLP, is a payment schedule where the buyer pays in stages as construction progresses, for example on booking, on plinth, on each slab and on possession, in place of paying the full price up front.
How much can a builder take before the agreement?
Under Section 13 of the Real Estate (Regulation and Development) Act, 2016, a promoter cannot accept more than 10 percent of the cost of the apartment as an advance without first entering into a registered agreement for sale.
Do this for the whole project.