Sheet 21 of 25 · RERA file · For buyers

Possession delayed? What RERA lets a buyer claim

If a developer misses the possession date, the law gives you a choice: stay and be paid interest every month, or leave with a refund. Here is how each works in Maharashtra.

RERA3 min readFigures as of 19 Nov 2026By the Bricko team
MARAPRMAYJUNPossession due+1 month lateInterest for every monthof delay, until possession
Sec. 18the section of the RERA Act that sets your options
MCLR + 2%interest rate in Maharashtra: SBI's highest MCLR plus 2%
0 daysfor the developer to pay once ordered
+4 months2026 extension that may affect the timeline

Few things are as frustrating for a homebuyer as a possession date that keeps moving. The RERA Act was written with exactly this in mind. Section 18 gives you two clear options when a developer fails to hand over the flat on the date in your agreement, and Maharashtra now has a procedure to make developers pay what they are ordered to.

01Your two options

  1. Option 1Stay in the projectYou keep your flat and the developer pays you interest for every month of delay, until you get possession.
  2. Option 2WithdrawYou get back everything you have paid, with interest, plus compensation as decided by MahaRERA's adjudicating officer.

Which is better depends on how far the project has got, whether you still want the flat, and whether you can afford to wait. A project that is close to completion and still selling is usually worth staying in. A stalled project with no progress for many quarters is a different decision.

02The interest rate

In Maharashtra, the rate of interest is the State Bank of India's highest marginal cost of lending rate (MCLR) plus 2%. It is the same rate a buyer pays the developer for late instalments, which is the point: the law treats both sides alike.

Illustrative arithmetic

Suppose you have paid ₹60 lakh and the applicable rate works out to 11% a year. Delay interest would be about ₹55,000 for every month of delay. Check the actual SBI MCLR on the date your claim is calculated.

03How to claim

  1. Write to the developer first. Ask for a revised date in writing and keep every reply.
  2. File a complaint online with MahaRERA, with your agreement, receipts and correspondence. Many disputes can also go to MahaRERA's conciliation forum first.
  3. Interest and refunds are decided by the authority; compensation is decided by its adjudicating officer.
  4. Appeals go to the Maharashtra Real Estate Appellate Tribunal.

04Getting paid after you win

Until recently, winning an order and getting paid were two different battles. Under the procedure MahaRERA adopted in November 2025, following Bombay High Court directions, the developer has 60 days to pay. If it does not, you file a non-compliance application, which is heard within four weeks. Recovery can then include attaching the developer's property, freezing bank accounts and civil prison of up to three months.

05The 2026 extension

In August 2026 MahaRERA gave registered projects with completion dates on or after 28 February 2026 an automatic four-month extension because of the West Asia conflict. It changes the timeline MahaRERA holds the project to. How it affects your own agreement's possession date and your interest claim is a question for an advocate, especially if your date fell in that window.

06Before you file

  • Collect the registered agreement, every payment receipt and all letters and emails.
  • Note the possession date in the agreement, and any extension the developer claims.
  • Read the project's quarterly progress updates on MahaRERA, and save them.
  • Talk to other buyers in the project; joint complaints are common and carry weight.
  • Calculate your interest claim month by month from the agreed date.

You can stay and be paid for waiting, or leave and be paid back. Either way, the clock runs in your favour.

Before you act on this

This article is general information as of 19 Nov 2026, not legal advice. Your rights depend on your agreement and the facts of your project. Speak to an advocate before you file a complaint.