Society redevelopment in Maharashtra: what the 2026 rules change

A new government resolution replaced the 2019 rules on 30 September 2026. Quorum, tendering, developer selection and bank guarantees all changed.

Policy & tax4 min readFigures as of 19 Nov 2026By the Bricko team
51%of all memberstwo-thirds quorum to meetSept 2026 GRreplaces the 2019 rules
0%of all members must approve the developer in writing
⅔quorum, with video attendance counted
0 daysto open tenders at a special general body meeting
0 monthsto sign PAAAs after the development agreement

Redevelopment is the biggest decision a housing society will ever take, and in Maharashtra it now runs on new rules. On 30 September 2026 the state's Cooperation Department replaced the government resolution of 4 July 2019, issued under Section 79A of the Maharashtra Co-operative Societies Act, which had governed redevelopment for seven years. It applies to developer-led redevelopment, self-redevelopment and cluster projects.

01Two layers of change this year

The new resolution sits on top of a wider reform. The Maharashtra Co-operative Societies (Amendment) Rules, 2026, notified on 18 June and in force from 30 June, added a separate chapter for housing societies and allowed members to join general body meetings by video. The September resolution then rewrote the redevelopment process itself.

02Meetings and votes

  • Quorum is two-thirds of members. Members attending by video count towards it.
  • Approval needs 51% of total membership, not 51% of those present. In a 100-member society, 51 votes are needed even if 75 attend.
  • Absent members' opinions cannot be counted.
  • Secret ballot: voting is normally by show of hands, but one-fifth of members can ask for a written secret ballot, conducted by the authorised officer at the society's cost.
  • Who decides: only a duly elected managing committee can take redevelopment decisions, not an administrator appointed by the Registrar.

03Tendering, step by step

  1. Within 30 daysProject report reaches the committeeThe secretary convenes a managing committee meeting. Members get at least 7 days to read the report and send suggestions.
  2. SGBMDraft tender approved by majorityThe tender must be approved at a special general body meeting.
  3. PublishAdvertise in Marathi and EnglishNewspapers with wide local circulation.
  4. Within 30 daysTenders opened at an SGBMPreviously 15 days, at a committee meeting. Fewer than three bids: extend by at least 15 days, then a further week.
  5. Vote51% of all members approve the developer in writingThe Registrar must decide on the society's submission within 14 days.
  6. PaperworkDevelopment agreement, then PAAAsBoth registered. Permanent alternative accommodation agreements within 3 months of the DA.
  7. At handoverAllotment by lottery at an SGBM14 days' notice, video-recorded; minutes and allotment list to the Registrar within a month.

04The bank guarantee is now yours to negotiate

The 2019 rules fixed the developer's bank guarantee at 20% of the redevelopment cost. That fixed figure is gone. The general body now decides the amount and the form. For strong societies in good locations, that is room to ask for more. For weaker ones, it removes a floor that used to protect them.

What societies should get in writing

The bank guarantee amount and its release stages; monthly rent and how it rises if the project runs late; the corpus; the carpet area each member gets, with the measurement standard spelled out; the completion date and the penalty for missing it. A project management consultant who works for the society, not the developer, is worth the fee.

05Self-redevelopment gets more support

Societies that want to redevelop themselves, without a developer, are also getting attention. In August 2026 the state notified rules that, Punekar News reported, let societies borrow up to ten times their land value. The 79A process still applies to self-redevelopment wherever there is a sale component.

06What it means for developers

Tender documents now need to work in Marathi and English, timelines are longer and more formal, and every vote needs a clean, recorded trail. Build that into the programme from the first meeting. A project that skips a step now risks being challenged later.

The new rules make redevelopment slower to start and harder to rush. That is the point.

Before you act on this

This article summarises published commentary on the 30 September 2026 government resolution and the 2026 amendment rules as of 19 Nov 2026. It is not legal advice. Read the GR itself, and take advice from an advocate before your society votes.